City of Alameda
Webster Street Renaissance Project
Weekly Construction Schedule Update  October 10
Contractor: Golden Bay Construction

Contacts:
City Public Works Department:  Greg Stoia, (510) 749-5928
City Development Services Department:  Sue Russell (510) 749-5834   
WABA:  Sherri Stieg (510) 523-5955
Golden Bay Construction: Michael Maldonado, Greg Pease, (650) 593-0310
Harris & Associates: Bill Frink, (510) 697-7082

WEEK OF OCTOBER 10, 2005

Description of Activity:
The contractor is expected to continue irrigation work and start planting at all mid-block plazas, bulbout corners and transit plaza planters. The work will progress throughout the project limits on Webster Street from Central Avenue to Pacific Avenue.

Location of Activity: 
Both sides of Webster Street from Central Avenue to Pacific Avenue.

Businesses Affected:
The work will have minimal impact on businesses on the both sides of Webster Street from
Central Avenue to Pacific Avenue.

Parking Changes
“Tow Away” and “No Parking” signs will be posted at various locations on Webster Street, from Central Avenue to Pacific Avenue.

Back to top | Close Window